Home > Ask a Question > Fix It Forum > Deck building question
Login | Register

Deck building question


Posted by Paul Minkler on April 25th, 2004 10:57 PM
In reply to deck building advice by K Street on August 21st, 2000 06:08 AM [Go to top of thread]

I am in the process of building a deck on a cross-sloping grade. On one end of the deck the joists are roughly 15 inches off the ground, and on the other end I have an inch at most from the ground to the bottom of the joist which doesn't leave any room for the beam. I'm cantilevering the deck so I need to dig below grade to make room for the beam. Is it ok to dig out for the beam, and is this common practice in working with a sloping grade? Any advice would be appreciated. Thanks.

Was this post helpful? Yes: or No: