My forms are set and ready for concrete for my footing. We had a thunder storm yesterday and my ditch filled with water. How long after the water drains should I wait before pouring the concrete. It is supposed to be 80 - 90 degrees for the next 4 days and then rain again. I'm working with clay.

thanks

Glenn Good

05:45PM | 05/13/05
Member Since: 09/10/03
314 lifetime posts
You should remove all water ASAP and scrape out any mud or loose material.

Allow the subgrade to dry completely before you pour.

Clay will shrink when it dries and could cause some settlement problems later on if it is not dry when you pour.

Glenn

Moderator: Construction Systems, Foundations, and Masonry & Stone

For more information about me and/or my qualifications please visit my website at:

www.consultationdirect.com


Post a reply as Anonymous

Photo must be in JPG, GIF or PNG format and less than 5MB.

Reply choose button

Anonymous

Post new button or Login button
Register